Dien Bien Agrees on Timeline and Responsibilities for Education Complex Project
On the morning of June 25, Comrade Nguyen Van Doat, Member of the Provincial Party Committee and Vice Chairman of the Provincial People's Committee, chaired a meeting with relevant departments, agencies and the investor to agree on the implementation timeline and responsibilities for the Dien Bien Education Complex Project. The meeting was attended by leaders of relevant departments, agencies and localities, along with representatives of FPT Education Company Limited.
At the meeting, representatives of FPT Education Company Limited reported on the project's implementation progress. The Department of Education and Training, which has been assigned by the Provincial People's Committee to monitor and expedite the project, presented a summary of the project's current status, results of assigned tasks, existing difficulties and proposed issues requiring consensus during implementation.

According to the report, the Dien Bien Education Complex is a land-use investment project developed under the cooperation policy between Dien Bien Province and FPT Corporation on education development, high-quality human resource training and digital transformation. The project will follow an integrated and multi-level education model, covering general education, vocational education and higher education.
The project is planned on land lot SDHH-01, adjacent to National Highway 12 in Dien Bien Phu Ward, covering approximately 10.57 hectares. Under the approved plan, the complex will have an annual training capacity of around 6,285 students and nearly 500 lecturers, teachers, officers and staff.
The project's preliminary total investment is estimated at more than VND 648 billion. It will be implemented over eight years in three phases. The project aims to enroll students and open its first training course in the 2027-2028 academic year, with full completion and synchronized operation expected by 2034.
To date, major legal procedures for the investor selection stage have basically been completed. The Provincial People's Committee has approved project information, the expression of interest documents, the results of the invitation for interest, and investor approval procedures in accordance with regulations.
At the same time, the province has applied the "green channel" mechanism for administrative procedures to shorten processing time for investment, land, environmental and construction-related procedures, thereby facilitating the investor's preparation process.
During the meeting, delegates discussed the project implementation schedule, compensation, support and site clearance, land allocation and lease procedures, detailed planning, environmental impact assessment, fire prevention and fighting appraisal, and conditions required for educational operations after project completion.
Participants agreed on the need to strengthen coordination between specialized agencies and the investor to promptly address difficulties and ensure implementation according to schedule. Representatives of FPT Education Company Limited requested the province to direct the acceleration of site clearance, technical infrastructure development and transport connectivity to the project area to ensure conditions for implementing project components as planned.
In his concluding remarks, Vice Chairman Nguyen Van Doat emphasized that the Dien Bien Education Complex Project is of great significance in improving the quality of human resources and meeting the province's socio-economic development needs in the new period.
He requested departments, agencies, localities and relevant units to continue closely coordinating with the Department of Education and Training and the investor to accelerate assigned tasks. Priority should be given to resolving difficulties in compensation, support and site clearance to ensure that clean land is handed over in the third quarter of 2026.
He also urged relevant agencies to promptly complete procedures related to land, environment, construction and other necessary requirements; effectively apply the "green channel" mechanism to procedures within their authority; and prioritize the completion of technical infrastructure connected to the project.
The Vice Chairman assigned the Department of Education and Training to continue serving as the focal agency for monitoring and expediting implementation progress. The department was also tasked with coordinating with relevant agencies and units to support the investor in completing requirements related to facilities, training programs and the establishment of educational institutions, ensuring the goal of enrolling students and opening the first course in September 2027./.