Temporarily closing Dien Bien Phu airport for about 6 months to invest in expansion

Dien Bien Phu Airport (Dien Bien province) is temporarily closed for six months from next March to carry out massive expansion work.

Dien Bien airport in the northern mountain province of Dien Bien.

This information was confirmed by Mr. Dinh Viet Thang, Director of the Civil Aviation Administration of Vietnam, to VTC News on the morning of January 27th.

Mr. Thang also added that in the coming time, he will complete the contractor selection, sign the contract of package No. 30 to construct the passenger terminal and ancillary works, package 34 for construction supervision, installation of construction equipment for passenger terminal...

According to Mr. Thang, some positions have not been constructed yet because the ground clearance has not been completed. "These locations, if constructed, will block people's roads and irrigation canals, so they will have to wait for site clearance, which will significantly affect the overall progress of the project," Thang informed.

In addition, the current source of materials for project construction is very limited, there are not enough reserves, while the licensing procedure for new material mines requires time.

In order to ensure the project progress as planned, ACV has proposed to the People's Committee of Dien Bien province to soon complete the site clearance work as well as soon complete the auxiliary works serving the people's lives (roads, irrigation systems, etc.) to avoid people obstructing the construction of works.

ACV also suggested that the People's Committee of Dien Bien province have a plan to supplement material sources to ensure sufficient reserves and ability to supply the project to deploy on schedule.

Previously, in September 2022, ACV started construction of the runway, taxiway, and apron under the construction investment project to expand Dien Bien airport. The project was approved for investment and construction to expand with a runway size of 2400m long, meeting technical standards for modern aircraft such as A320, A321.

At the same time, renovating and expanding the operating capacity of the existing passenger terminal from 300,000 passengers per year to 500,000 passengers per year; renovating and building new auxiliary works, civil aviation zone to ensure synchronous operation of A320, A321 and equivalent aircraft./.

Source: VTC News