Meeting to review progress of the Nam Rom River Basin Multi-Hazard Management Project

On the morning of December 22nd, the People’s Committee of Dien Bien Province held a meeting to review the progress of the project “Multi-Hazard Management of the Nam Rom River Basin to Protect Livelihoods, Adapt to Climate Change, and Promote Socio-Economic Development in Dien Bien Province”, which is funded by ODA loans from the French Development Agency. The meeting also discussed solutions to address difficulties and obstacles arising during project implementation.

Comrade Lo Van Cuong, Member of the Standing Committee of the Provincial Party Committee and Permanent Vice Chairman of the Provincial People's Committee, delivered the concluding remarks at the meeting.

On the morning of December 22nd, the People’s Committee of Dien Bien Province held a meeting to review the progress of the project “Multi-Hazard Management of the Nam Rom River Basin to Protect Livelihoods, Adapt to Climate Change, and Promote Socio-Economic Development in Dien Bien Province”, which is funded by ODA loans from the French Development Agency. The meeting also discussed solutions to address difficulties and obstacles arising during project implementation.

Mr. Lo Van CMember of the Provincial Party Standing Committee and Standing Vice Chairman of the Dien Bien Provincial People’s Committee, chaired the meeting and delivered the concluding remarks. Participants included representatives of leaders from relevant departments and agencies, the People’s Committees of Dien Bien Phu Ward and Thanh Yen Commune, and related units.

According to reports, the Nam Rom River Basin Multi-Hazard Management Project has so far completed the construction of Weirs No. 1 and No. 2; completed 8.4 out of 14.6 kilometers of embankments; basically completed dredging from Weir No. 1 to the existing weir; and finished construction in the area from Weir No. 1 to Thanh Binh Bridge, including slope protection, walking paths, railings, and lighting systems. The capital plan allocated for 2025 amounts to more than VND 147 billion, of which over VND 100 billion has been disbursed, reaching approximately 68% of the plan. The Project Management Board (PMB) for Agriculture and Rural Development Works committed to disbursing 100% of the allocated capital by January 2026.

The head of the Department of Agriculture and Environment spoke at the meeting.

Regarding compensation and site clearance, the total land area to be recovered for the entire project is 88.33 hectares, involving 521 households, organizations, and individuals. To date, compensation plans have been approved for 66.08 hectares (74.8%); 59.78 hectares have been handed over (67.68%); and 12.08 hectares remain pending. The total land area handed over to the project is 76.25 out of 88.33 hectares, reaching 86.23%. The PMB requested relevant units to urgently complete documentation and accelerate the preparation, appraisal, and approval of compensation plans as a basis for payment and site handover to contractors, while strengthening communication and mobilization efforts to encourage people to comply with policies on compensation and site clearance.

At the meeting, the Project Management Board (PMB) proposed that the Provincial People’s Committee allow an extension of the project implementation period until the end of October 2027, as site clearance has been slow and handed-over land plots are not contiguous, causing difficulties for construction. It is expected that the project cannot be completed according to the originally approved schedule, which was the end of 2025. In addition, the allocated capital plan remains insufficient and has not yet been supplemented. The Provincial People’s Committee is directing adjustments and additions to several items to complete the lighting system and landscape in the area from upstream of Thanh Binh Bridge to A1 Bridge, creating highlights to attract tourism; therefore, project adjustment dossiers need to be completed and submitted for approval.

Leaders of Thanh Yen commune discussed the difficulties and obstacles of the project implementation in the commune.

During discussions, departments, sectors, and localities clarified the progress of each contract package, project completion milestones, emerging difficulties, and proposed solutions for the coming period.

Concluding the meeting, Standing Vice Chairman of the Provincial People’s Committee Lo Van Cuong requested the PMB for Agriculture and Rural Development Works to continue proactively coordinating closely with departments, sectors, and local authorities of communes and wards within the project scope, focusing on accelerating site clearance progress. He also directed construction units to organize work in “three shifts, four teams,” ensuring that once residents reach consensus, compensation payments are made promptly and construction is immediately commenced.

For Thanh Yen Commune, it is necessary to work with each household individually, review each case, and intensify communication on the objectives and significance of the project. He agreed with the proposal of the Department of Agriculture and Environment to assign two officials to coordinate with Thanh Yen Commune authorities to resolve difficulties and obstacles. In Muong Thanh Ward and Dien Bien Phu Ward, communication efforts should continue to be strengthened, and the remaining compensation plans should be approved soon to ensure payments are made in accordance with regulations./.