Dien Bien Province

Meeting of the Steering Committee on the implementation of the Nam Rom River Basin Multi-Hazard Management Project

On the morning of October 11, the Steering Committee for the implementation of the “Nam Rom River Basin Multi-Hazard Management Project to protect livelihoods, adapt to climate change, and promote socio-economic development in Dien Bien Province," funded by the French Development Agency (ODA loan), conducted a field inspection and held a meeting to assess the project's implementation progress. The meeting was chaired by Mr. Lo Van Tien, Vice Chairman of the Provincial People's Committee and Head of the Steering Committee.

Mr. Lo Van Tien, Vice Chairman of the Provincial People's Committee, delivers a speech at the Steering Committee meeting.

According to the report from the Project Management Board for Agricultural and Rural Development Works, land clearance for the project in Dien Bien District involves the recovery of land from 285 households and organizations across four communes (Thanh Hung, Thanh Chan, Thanh Xuong, Thanh Yen). Compensation and land clearance plans for 119 households have been approved. In Dien Bien Phu City, the project affects 291 households and organizations across six wards and communes. To date, construction has commenced on 5 out of 7 contract packages, including packages 2, 3, 4, 5, and 6. Package 1 lacks available construction land, and package 7, involving dredging, will begin after the embankment is built. The current construction value is 114.4 billion VND out of a total of 656.823 billion VND, reaching 17.42% of the contract value.

Mr. Nguyen Huu Hiep, Director of the Project Management Board for agricultural and rural development works, reports on the project's progress.

During the project’s implementation, numerous challenges have arisen, particularly in the slow process of compensation and land clearance, which has hindered the progress of the contract packages. As of now, only 119 out of 285 households in Dien Bien District have received approval and compensation, while Dien Bien Phu City has yet to approve any. The verification of land origins in the wards is slow, and management of land along the riverbanks by local authorities is still insufficient, allowing residents to reclaim and cultivate on this land. In Dien Bien District, the verification of land origins by the communal People's Committees, the determination of the time of asset creation, and the verification of the number of households and individuals directly engaged in agriculture are all progressing slowly.

Speaking at the meeting, Mr. Lo Van Tien, Vice Chairman of the Provincial People's Committee, praised the responsible attitude of local authorities and the project investors in implementing the project. To accelerate the project’s progress, in the coming period, it is crucial to strictly implement the conclusions made by the Chairman of the Provincial People's Committee at previous meetings. The Project Management Board for Agricultural and Rural Development Works is urged to coordinate with the People's Committee of Dien Bien Phu City and the People's Committee of Dien Bien District to expedite the land clearance process as quickly as possible. The People's Committee of Dien Bien District must take decisive actions to resolve the land clearance issues thoroughly.

Mr. Lo Van Tien, Vice Chairman of the Provincial People's Committee, inspecting the site of contract Package 2 of the Nam Rom River Basin Multi-Hazard Management Project.

Later that morning, the delegation conducted a field inspection of the Nam Rom River Basin Multi-Hazard Management Project, which aims to protect livelihoods, adapt to climate change, and promote socio-economic development in Dien Bien Province./.