Investment plan for Moc Chau - Son La - Dien Bien expressway

The Ministry of Transport has recently provided information on the implementation plan for the investment preparation of the expressway project connecting Moc Chau, Son La City, and Dien Bien. According to the national road network plan for the 2021–2030 period, with a vision to 2050, the Moc Chau - Son La City expressway is 105km long, with a scale of 4 lanes, and is planned for investment before 2030.

Perspective of the Hoa Binh - Moc Chau expressway under construction - Photo: Provided by the unit

Affirming the necessity of investing in this expressway and maximizing the effectiveness of the Hoa Binh - Moc Chau Expressway currently under construction, the Ministry of Transport stated that during the formulation of the medium-term public investment plan for 2026–2030, based on the ability to balance resources and the principles of fund allocation as regulated, the Ministry will report to competent authorities to prepare and allocate investment funds for this expressway.

Regarding the Son La - Dien Bien expressway section, according to the road network plan, this expressway will be 200km long, with a scale of 4 lanes, and its investment schedule is set for after 2030.

The Prime Minister, in Document No. 538/TTg-CN dated June 23, 2022, assigned the People's Committee of Dien Bien Province as the competent authority to implement the Son La - Dien Bien - Tay Trang Border Gate Expressway Project. Phase 1 covers the section from Dien Bien Phu City to the Km15+800 intersection on National Highway 279, with a length of about 44km, under the BTL contract model (Build-Lease-Transfer) during the 2022–2030 period.

Searching and mobilizing legitimate funding sources

The Ministry of Transport will coordinate and support Dien Bien Province and investors in the research and finalization of the investment plan for the mentioned project. At the same time, the Ministry will work closely with other ministries, sectors, and localities to search for and mobilize legitimate funding sources to quickly implement the Son La - Dien Bien expressway section according to the plan.

For the Hoa Binh - Moc Chau Expressway project, the section passing through Hoa Binh Province is 34km long. The Phase 1 investment is scaled for 2 lanes, with a total investment of VND 9.777 trillion, divided into two construction packages (XL01, XL02).

On September 29, 2024, Hoa Binh Province held the groundbreaking ceremony to begin construction of package XL-013. Currently, contractors are conducting surveys, preparing construction drawings, building service roads, and establishing the construction site, with implementation at section Km24+500-Km27+500 and position Km38+400.

The section passing through Son La Province is 32.3km long, with a Phase 1 investment of VND 4.938 trillion, also scaled for 2 lanes. The project is currently in the process of preparing documents, surveying, inventorying compensation, supporting resettlement and land clearance, and selecting contractors for consulting packages./.

Source: Chinhphu.vn 

 