Dien Bien Province

Commencement of construction and expansion of Dien Bien airport in December 2021

Airports Corporation of Vietnam (ACV) said that the construction of the expanded Dien Bien airport project is scheduled to begin in December 2021 and finish at the beginning of the fourth quarter of 2023. The total implementation time will last in 30 months, four months fewer than the initial plan.

Construction of the expanded Dien Bien airport project to begin in December 2021.

ACV Deputy General Director Do Tat Binh said that on March 27, 2021, the Prime Minister issued Decision No. 470 approving the investment policy of the construction project to expand Dien Bien airport. The airport will be upgraded to receive large aircraft such as Airbus A320s and A321s and those with equivalent sizes; renovate the existing station to meet the capacity of 500,000 passengers per year with synchronously built technical infrastructure works.

The ACV is the investor of the project which is estimated to cost VND1,547 billion (US$67 billion), operation term is 50 years. According to the Prime Minister's Decision, 34 months after approving the policy, ACV must complete the project investment.

According to the master plan developed by ACV, the project is expected to be approved in August 2021, before completing the design and estimation procedures in November 2021. The contractor selection and project start-up will be done in December 2021.

As for the station, it is expected to start construction in December 2022; The airport is expected to close in March 2023 for the construction of the terminal and the remaining items of the airport.

"The project implementation progress is guaranteed and it is expected that the project will be started in the fourth quarter of 2021, completed at the beginning of the fourth quarter of 2023, the total implementation time will last in 30 months, four months fewer than the initial plan" said Mr. Do Tat Binh.

Regarding site clearance, Mr. Le Thanh Do, Chairman of Dien Bien Provincial People's Committee said that the Provincial People's Committee had approved the site clearance project, resettlement support and resettlement site construction projects according to the detailed planning. It is expected that Dien Bien province will hand over the entire ground area for the construction of taxiways, take-off/landing lanes and aprons in advance according to the plan to upgrade Dien Bien airport before August 30, 2021.

Regarding the capital source for the project, ACV Chairman Mr. Lai Xuan Thanh said that ACV has balanced enough capital to deploy the construction and expansion of Dien Bien airport right after the investment policy is approved. This enterprise also committed to balance to ensure sufficient financial resources for the project, ensuring the project progress.

The Dien Bien Airport, 500 kilometers to the west of Hanoi, is the largest and the only commercial airport in the northwestern region of Vietnam. 

It was originally a military airport built in 1954. It began commercial operations in 1994. It has one 1,830-meter runway that can handle short-haul ATR72 and smaller aircraft. Its current capacity is 300,000 passengers per year./.

Source: Chinhphu.vn

 